8/8/19: The second lift of paving will occur later this year. The paving was delayed due to the 149th pavement failure that needed to be restored first.
7/2/19: Pedestrian ramps on the bike path will be paved today, weather permitting.
10/26/18: Paving was completed.
10/17/18: Curb is scheduled to begin 10/17/18
8/22/18: Resident notice mailed out regarding Start of Construction Construction Notice.
6/19/18: Ham Lake City Council accepted the Street Reconstruction project. The low bidder is Douglas-Kerr Underground, LLC. A project schedule will be posted when available.
2/7/18: The Contractor is scheduled to begin tree removal on Monday 2/12.
2/2/18: Surveyors will be on site marking trees and staking/flagging areas to be cleared on Monday, February 5th. The contractor plans to begin tree clearing work on Wednesday, February 7th. A resident notice was sent out today which can also be viewed by clicking Resident Notice.