9/15/2017: Concrete curb and gutter will be poured Wednesday, September 20th.
9/13/2017: Concrete curb and gutter is expected to be poured on Monday, September 18th. Please do not drive on or over the fresh concrete for a minimum of 72 hours.
9/5/2017: Douglas-Kerr Underground will be onsite September 11th.
8/23/2017: Douglas-Kerr Underground will be offsite from August 24th through September 1st.
8/21/2017: During the installation of the storm sewer, the contractor found organic soils. It is standard engineering practice to complete soil corrections. Starting 8/21/2017 through 8/25/2017 the contractor will be removing all of the organic material below the new roadbed and replacing with sand. Through access of Ulysses Street may be temporarily closed throughout the week. Once the soil corrections are completed, the road will be covered with class 5 aggregate base.
8/1/2017: The contractor has been installing new storm sewer this week and will continue until Friday August 4. Through access of Ulysses Street may be temporarily closed throughout this week.
7/19/2017: A second revised construction schedule was received July 19th and can be viewed by clicking the "Schedule" hyperlink below.
7/6/2017: A revised construction schedule was received on July 5th and can be viewed by clicking the "Schedule" hyperlink below.
6/26/2017: The construction start has been delayed to the first week of July 2017.
6/6/2017: The contractor plans to begin road work the week of June 26, 2017. Their schedule can be viewed by clicking the "Schedule" hyperlink below. A resident notice was sent out today which can also be viewed by clicking Resident Notice