167th Avenue, Fraizer Street and 165th Avenue Street Construction
Lead Engineer: Tom Collins P.E.
E-mail: tcollins@rfcengineering.com
Office: (763) 862 - 8000
The Prime Contractor is Asphalt Surface Technologies (ASTECH) and the contact is:
Lance Bemboom - Project Superintendent
Office: (320) 363-8500
Mobile: (320) 248-7720
Approved Plans
Schedule
6/12/19: The second lift of asphalt is scheduled to be completed in late July. The website will be updated with the exact dates closer to the day.
6/12/19: Seeding is scheduled to be completed in the next week. There has been issues contacting the subcontractor to complete this work.
5/1/19: Spring construction is anticipated to begin May 6th, weather permitting.
11/13/18: Paving is postponed until 2019. Contractor will complete temporary mulching of disturbed areas and ramping driveways this week or early next week.
11/8/18: Roadway paving scheduled for November 12th and 13th. Driveway paving scheduled for November 14th.
11/7/18: Paving scheduled for week of November 12th.
10/29/18: Final grading finishing up this week. Paving anticipated to be done November 7th.
10/17/18: Concrete spillways and driveways were poured.
10/16/18: Concrete curb and gutter was poured.
7/25/18: Property owner notifications mailed out.
7/25/18: Tree clearing is scheduled to begin July 30th.
6/11/18: The Contractor anticipates that construction wil ocmmence in late July or early August.
6/4/18: The City Council awarded the project to ASTECH.
5/31/18: Bids will be opened at 11:00 am.
5/10/18: The advertisement for bids posted in the Star Tribune.
5/7/18: City Council approves plans and authorizes the advertisement for bids.