2302.038 - County Ditch #58 - 152nd Avenue Cross Culvert
Lead Engineer : David Krugler P.E.
E-mail: dkrugler@rfcengineering.com
(763) 862 - 8000

7/26/24 - The box culvert has been fully installed. Backfilling around the box culvert is currently happening.

7/25/24 - The box culvert is being istalled today.

7/24/24 - The aggregate bedding for the box culvert is being installed today. Installation of the box culvert sections will begin Thursday 7/25/24.

7/22/24 - The creek is now low enough to remove the existing culverts. The creek will temporarily be bypassed to the east side of the project. The box culvert sections will start arriving on site Thursday 7/25/24 at the earliest.

7/11/24 - The creek bypass pipe was installed on 7/10/24. The creek's water level needs to come down a few more inches before the creek can be temporarily diverted.

7/1/24 - The creek's water level is still too high to remove the existing pipe and temporarily divert the creek around the construction area.

6/24/24 - Dewatering methods are being installed today. Once the creek water levels are lower, the existing culvert can be removed.

6/11/24 - Tree clearing is scheduled for today.

6/10/24 - Centerpoint will be installing the new gas line.

5/28/24 - Survey staking to begin.

5/2/24 - The contractor has provided their planned construction schedule, which can be found here County Ditch #58 Culvert Replacement Schedule.
The planned start date is June 3rd. The dates within the schedule are subject to change depending upon weather and contractor scheduling.

4/8/24 - Resident letters mailed with project details and contractor.

4/4/24 - The project was awarded to Northdale Construction at the April 1st City Council Meeting. The starting date has not yet been determined but will be updated as information becomes available.

Resident Notice Project Information
Approved Plans



 

 
The above information will be maintained as up to date as possible.