Lund's Lakeview Forest Reconstruction
Lead Engineer : David A. Krugler, P.E.
(763) 862 - 8000

9/16/2021: Curb is planned to be installed on the remainder of 160th Lane on Monday, 9/20/21. Bituminous driveways are planned to be paved on Wednesday, 9/22/21. Please avoid overnight parking on the driveways for Wednesday night.

9/13/2021: With weather permitting, paving is planned to begin on Thursday, 9/16/2021. Please avoid over night parking on the road for Thursday night.

8/31/2021: Due to equipment failure today, the curb was not started as planned. The contractor plans on starting curb installation on 9/1. Openings will be provided for all driveways wide enough for vehicles due to the timing of the installation to allow 24/7 access to residental properties for any curb poured this week.

8/27/2021: Due to the rain this weekend, curb installation is planned to begin 8/31.

8/20/2021: Veit will NOT be pouring curb on 8/23 & 8/24. The contractor has rescheduled curb for 8/30.

8/17/2021: Veit will be pouring curb starting 8/23. Notices are being sent out to residents, or is located here

8/3/21: Veit will being installing storm sewer along Zumbrota betwen 159th Avenue and 160th Lane. They will also beginning preping the road base.

7/28/21: Veit plans to begin installing storm sewer on August 2nd.

7/8/21: Project Construction Resident Notice mailed out. Construction Resident Notice

6/30/21: Utility relocation is occurring ahead of main construction. Veit is tentatively planning to begin installing storm sewer July 19th.

6/9/21: The contract was awarded to Veit Companies at the June 7th City Council meeting. Project work expected to begin in July. Utility work expected June through July.

5/11/21: Request for bids were announced for contractors to provide their bids for the project. Bids will be opened on June 3rd and the City Council will vote to approve/reject at the June 7th City Council meeting.

3/3/21: Notices were sent to residents regarding tree removal in preparation of the project. Oak Trees need to be down by March 31st to prevent the spread of Oak Wilt.
Resident Notice
Tree Removal Plans

8/17/20: Wetland delineation, geotechnical investigation and topographic survey to begin in the upcoming weeks.

Approved Plans



 

 
The above information will be maintained as up to date as possible.