2105 - Creek Valley Reconstruction Lead Engineer : Luke Zellmer (763) 862 - 8000
September 27, 2022 - Some utility relocation will be happening on the site to avoid conflicts with the construction next year. Comcast is already done with their relocates and will clean up/reseed after themselves. The City will come and remove the survey lath.
August 8, 2022 - The prime contractor, Douglas-Kerr Underground, has indicated construction will not commence until Spring 2023. Tree stumps will be removed by Rivard Contracting in conjunction with Public Works in upcoming weeks.
June 16, 2022 - Notices have been sent out via mail to inform residents of updated project timelines.
March 11, 2022 - Rivard Construction will be performing the tree clearing portion of the road construction project due to the Ham Lake Oak Wilt requirement that no oak trees are to be removed between April 1st and July 15th.